MPC
Komiya president Eguchi adviser everyone
everyday it becomes very indebted from.
The weekly work report NO99 we attached.
And sorry to trouble you, but, please confirm.
1, the waste water from the laundry, the factory will consider reviewing the test value from to the production
environment corrective work on 2,2D building assembly area
cleaning chamber is adjust to the clean room and the environment equivalent to
the cleaning chamber and clean room <<< mounted between differential pressure gauge. Differential pressure gauge is get paid than MPC like
relocation plan 3, and air conditioning in the wash chamber after the completion of the cleaning chamber around construction work in MPC-1 Canteen.
<<< Please consider the time that can be removable.
4,2D Building 2F (in a clean room) designed to be independent broadcast facility a.
Only to scheduled broadcast clean room is to be able to.
July 17 (Sunday) installation is complete.
<<< Get a schedule of instruction than MPC-like
broadcast microphone and submit additional speaker of quote
5, MPC-1 roof repairs
<<< November 11, purchase order acceptance
cleaning of waterproof place from November 22, the underlying process start.
The scheduled start of the underlying paint from next week
6, MPC-2 300 ton press construction
<<< November 16, the rising wall, concreting of the press foundation part
finish of the pit, in the mounting of the angle bar corner.
7, MPC-1 private fire fighting equipment work
<<< excavation work started in November 16,
November 26, foundation concrete placement plan. Material loading of the piping material.
8, and then mounting the ladder for the roof inspection to MPC-2 Canteen building.
(MPC-1, MPC-2 whole building, we become to use the inspection of the roof can be.)
Or more and will you, but your request, please take my name is anything if you have had you pointed out etc .. seat.
Thank you.
Dharma Construction Honda